Expansion of the electricity grids in the Spanish Basque Country is expected to cost just under €1.3 billion. The parties involved aim to increase the grid’s capacity by 50 per cent by 2030 through these investments. Representatives of the regional government, provincial administrations and grid operators presented the plans on 25 November in Bilbao and set up a working group for coordination.
The body is to draw up a timetable for priority investments and speed up implementation. In addition to the Basque government and provincial administrations, it includes the transmission system operator Red Eléctrica and i-DE, the distribution grid company of the energy company Iberdrola.
According to Red Eléctrica, around €370 million is allocated to the transmission grid. Javier Arriola, i-DE’s regional director, put his company’s planned investment in the distribution grid between 2027 and 2030 at around €900 million. The money is to go towards reinforcement and digitalisation, and enable additional connections.
Iberdrola estimates that work on the distribution grid across the value chain will require a total of 18,000 jobs to be mobilised by 2030. This is an employment estimate; it does not show that an equal number of new, permanent jobs will be created.
The basis is the transmission grid plan adopted by the Spanish Council of Ministers on 20 November. According to the Basque government, it provides for an additional grid capacity of up to 6,000 megawatts in the region. This would represent an increase of half compared with current capacity. The government lists more than 20 measures at existing substations and ten new substation facilities.
The projects affect the provinces of Álava, Bizkaia and Gipuzkoa. As examples, the regional government cites a new facility south of Vitoria-Gasteiz and an expansion of the Gatika substation. Modernisation in Santurtzi and a stronger connection to Ortuella are also intended to support the electrification of the Port of Bilbao. In Azpeitia a new substation is planned.
Industry Minister Mikel Jauregi cites the economy’s growing demand for electricity as the reason for the expansion. According to the regional government, 117 energy-intensive companies have reported additional connection needs to switch their production. The government also expects benefits for housing construction and transport. These effects depend on the planned facilities actually being implemented.
Editor: Mira Cadena (Article created with AI assistance).