Navarra prepares to build second tube for Almandoz Tunnel

The Regional Government has approved the tender for construction works worth around €87.2 million. Construction is scheduled to begin in 2027.

The regional government of Navarre has approved the tender for a second bore of the Almandoz Tunnel The estimated value of the construction contract is €87.25 million, including VAT. The works are expected to take 36 months and are due to begin in 2027.

The regional minister responsible for territorial cohesion, Óscar Chivite said on 25 November that the tender was expected to be published in the coming weeks. According to a report by elDiario.es, he expressed the hope that work would begin before summer 2027. No firm start date has therefore been set. Nor has the construction contract been awarded simply by approving the tender.

The Almandoz Tunnel is on the national road N-121-A, with Pamplona which connects northern Navarra and runs via Irún towards France. The regional government justifies the expansion on the grounds of the road safety and European safety requirements for tunnels on the trans-European road network.

According to the published plans, the new bore is to be around 1,350 metres long and run parallel to the existing tunnel. Connecting galleries are to link the two bores at intervals of about 400 metres. The central gallery is also to be passable for heavy vehicles, while the others are intended for pedestrians. According to the information provided, the construction contract also covers these connections and their facilities.

A separate services contract is planned for the management, supervision and monitoring of the construction work. Its estimated value is around €3.05 million, including VAT, and its planned duration is 39 months. According to the regional government, no further expropriations are needed for the project because the required land was already acquired as part of the overall project.

The expansion of the route also includes the Belate-Tunnel. For its second bore, the regional government approved a contract on 18 November to prepare a new completion project and subsequently supervise construction. The original construction contract was terminated in October. The amount cited for this, around €1.7 million, should be distinguished from the costs for Almandoz.

Construction is already under way on the section between the two tunnels. According to the published information, €15.9 million has been allocated for this. No completion date for all the sub-projects together has been announced.