Several factors have increased the cost of Madrid motorway tunnel

An investigation by elDiario.es cites reasons for the increased cost of tunnelling the A-5 motorway. In October, the city of Madrid approved more than 33 million euros in additional funding.

Unrecorded utility infrastructure, inaccurate planning documents and additional connection work have, according to an investigation by elDiario.es the tunnelling of the A-5 motorway in Madrid more expensive. The report, published on 16 November, explains the breakdown of additional costs that the city had already approved in October 2026. It says the city approved a combined additional sum of more than €33 million, including VAT, for two construction sections.

The latest news is the new information about the cost items, not a new funding decision. The local news outlet Somos Madrid reports that it obtained access to 417 items. In them, the construction companies justified work that had not been included in the original contracts and for which the city had accepted additional payment.

According to the investigation, some of the additional costs relate to existing infrastructure that had not been identified during preparation. Inaccuracies in the original documents are also said to have made changes necessary during construction. The report cites interruptions to the water supply and additional work to connect the Paseo de Extremadura to the ring road M-30.

A city decision dated 22 October confirms additional expenditure of around €16.55 million for the second construction section. The city cites unforeseen circumstances, particularly those relating to existing utility infrastructure. The contract amendment extends the construction period for this section by four months.

The deputy mayor and city spokesperson Inma Sanz defended the cost increase at the end of October. Changes were common in major construction projects, she said, according to Europa Press. Among other things, water pipes, high-voltage power lines and telephone cables had to be replaced or moved.

The project Paseo Verde del Suroeste is intended to route the motorway, which currently runs above ground, through a tunnel and create a green urban space above it. The city aims to reduce the barrier between neighbouring districts. According to elDiario.es, the total bill for the construction work, including the additional costs, is approaching €400 million; this is not a final account.

Since 10 November, the new tunnel has been connected to the existing M-30 tunnel. The connection is closed until 23 December, according to the city. The tunnel is due to open to traffic on that day. The opening to traffic should be distinguished from the later completion of all the contracted work.